Ladycross Infrastructure Enhancements

Project Overview:
This extensive project in North Yorkshire was divided into two key locations, focusing on infrastructure improvements while adhering to the environmental standards of the North York Moors National Park.

Key Works Undertaken:

Location One – A171 Coastal Road to Whitby:

  • Installed a new centre lane to facilitate safer traffic exit from the A-road.
  • Implemented a full verge drainage system.
  • Laid conservation kerbs to maintain the area’s aesthetic integrity.

Location Two – Near Egton Village:

  • Conducted topsoil stripping and subsoil excavation to formation level.
  • Installed 6F5 capping and Type 1 subbase using Trimble GPS-guided equipment.
  • Constructed a swale parallel to the new access entrance, complete with headwalls, check dams, filter drains, and carriageway gullies to manage water egress effectively.

Located on the A171 heading to Whitby, MWS completed the S278 works and temporary haul road installation for Esh Construction Limited. The project involved widening the main road to introduce a ‘ghost lane’, and the installation of a new entrance off a nearby B road to make HGV access possible to a new Polyhalite Mine. Works included the installation of all kerbs, gullies, drain runs, filter drains, swales, headwalls, and check dams, as well as full depth pavement construction, all delivered under Traffic Management restrictions and within Programme.

Results:
The project successfully enhanced road safety and access while preserving the natural landscape, meeting both infrastructural and environmental objectives.